HULK DEFENSEUncrewed underwater vessels

Programme

Six revisions of design development, a frozen configuration, and a first vessel entering construction.

Where the HD-18 is

The design is frozen at V10 and the first vessel is entering construction. Configuration, structure, arrangement and the full bill of materials are released.

Build slots in the first series are open now. Configuration is set per customer — payload fit, sensor package, endurance profile and delivery position.

Design maturity

Six revisions, and what each one settled.

Revision ADesign study. Envelope, displacement and the broad architecture established.
Revision BPayload architecture resolved: dry compartments loaded on the surface, chosen over an opening bay for stability and simplicity.
Revision CDeck arrangement and closure design developed through to a full structural take-off.
Revision DArrangement reworked: payload moved to dry wells loaded on the surface, the section re-cut so hatches land on flat deck, ring frames moved onto the bulkhead stations, and the mast designed as a system rather than a weight allowance.
Revision EConfiguration frozen: three sealed pressure-balanced compartments, six upward-hinging dogged hatches, a three-stage mast on its own trunk. Full CAD, drawings and costed bill of materials released.
Revision F / V10Architecture settled. The battery moved forward, which closed the trim and cleared the parallel middle body of everything except payload — so the hull became stretchable, and the six-to-twelve-bay family was solved in full. Compartments deepened to 1.45 m so a module can stand on its lift and rise clear of the coaming without anyone entering the boat. Sourcing re-verified line by line against live vendor pages.

Build sequence

Seventeen stages, and three of them are gates.

The order is not a preference. The ring frames must be set before the compartments can be landed, because the flange mounts land on the frames. The compartments must be proof-tested before installation, because a compartment cannot be tested in place. And the hatch seats must be machined and lapped after the compartments are installed and aligned, because the six seats have to end up in a plane with the deck.

The critical path is not the labour. It is the first-article hatch and the long-lead procurement, and both are gated on the design freeze. A programme that releases six hatches on a paper design saves nothing and risks everything.

5,978 hours of direct labour are carried across engineering, fabrication and assembly, and the procurement lines carry published lead times. Those two things are what a schedule can honestly be built from.

In build — the faired hull on its cradles with one cover raised
In build — the faired hull on its cradles with one cover raised
  1. Design freeze

    Production drawings, welding procedure and welder qualification to EN ISO 15614-2.

  2. Long-lead release

    Thrusters, generating set, cells, motors, compressor, sonar, velocity log and inertial unit — the published lead times, not an estimate.

  3. Structure

    CNC plate profiling; 8 ring frames and the space frame welded, fitted and aligned.

  4. Compartments

    Fabricated off the vessel, non-destructively tested, and hydrostatically proof-tested individually to 3.017 bar.

  5. First-article hatch

    One hatch fabricated, machined, assembled and pressure-tested before the other five are released. This is a gate, not a milestone.

  6. Tankage

    Tank boundaries and bulkheads fabricated and coated — 34.7 m³ gross.

  7. Landing

    Compartments landed on the four-point flanges and aligned. The alignment sets the hatch seat plane.

  8. Closures

    The remaining five hatches fabricated, all six coamings machined, seats lapped and dogs set.

  9. Machinery

    Generating set pod, battery pods, propulsion, thrusters, control planes and mast trunk installed.

  10. Air plant

    Bottles, compressor, regulator trains, relief and monitoring installed, commissioned and fault-case tested.

  11. Electrical

    Harness installation, junction boxes and the compartment connector interfaces.

  12. Fairing and coatings

    Hull fairing fitted and faired off; etch primer, barrier coat, copper-free antifouling and cathodic protection over 273.5 m².

  13. Integration

    Systems integration, software and autonomy commissioning.

  14. Ballast

    19,750 kg of fixed ballast grouted into the keel channel at the solved longitudinal centre.

  15. Inclining

    Inclining experiment and trim verification — the only physical check on KG that exists before the first dive.

  16. Dock trials

    Every sealed volume tested in the water at shallow immersion, with the vessel recoverable by crane, before any depth is attempted.

  17. Sea trials

    Two weeks with a support craft. Powering, endurance, dive and surface cycles, autonomy, communications, and the pressure-balance fault cases exercised deliberately rather than encountered.

Assurance

One compartment unit — the sealed box, two trunks rising to the seat, two covers flush with the deck
One compartment unit — the sealed box, two trunks rising to the seat, two covers flush with the deck

What gets tested, and what is still an open question.

The obligations below are scoped and costed regardless of which certification regime ends up applying. They are what any competent review would impose on a pressure boundary, and they are in the programme already.

The regime itself is deliberately open. An uncrewed submersible carrying commercial cargo does not sit cleanly in any established category: it is not a manned submersible, not a conventional cargo ship, and not a small uncrewed surface vessel. We have not invented a determination we do not have. The classification line in the programme is the cost of finding out, not the cost of complying — and getting that answer in writing from the intended flag administration is the single most valuable thing the programme can do next.

Welding procedure and welder qualification
EN ISO 15614-2, through a notified body
Weld NDT — dye penetrant
Every compartment seam
Weld NDT — radiography
A sample of butt welds
Hydrostatic proof test
Each compartment to 3.017 bar — 1.5× the full unbalanced head
Pressure-balance fault-case testing
Commissioning against every declared failure mode
Inclining experiment
Verification of KG and the ballast solve
Dock trials, leak and immersion test
Every sealed volume, before any depth
Cathodic protection design
Bonding and anode sizing to 273.5 m²
Classification liaison
Held open deliberately — see below

Ownership

The design is ours, end to end.

Hull form, structure, arrangement, closure design, energy system and payload interface were all developed in-house against one engineering model. There is no licensed platform underneath and no third party to renegotiate with.

That matters when a customer wants the boat changed: length, payload volume, endurance and sensor fit are parameters in the model, not a redesign. The six-to-twelve-bay family is the proof — four full solves of the same architecture, produced by changing one number.

Discuss a configuration

Plan view — three pairs of covers on the flat deck, mast trunk forward of the stern group
Plan view — three pairs of covers on the flat deck, mast trunk forward of the stern group
Alongside with two covers raised and modules standing proud of the deck
Alongside with two covers raised and modules standing proud of the deck